The process plant is operated and maintained by our own team consisting of 106 employees.
Material mined is processed via a traditional crushing and grinding circuit followed by a carbon in leach circuit for gold recovery. The rated capacity of the plant is 1,000 tpd, however, higher rates of up to 1,200 tpd have been realized. Gold recovery is expected to average over 90%.
Power for the plant and other services is provided by five 1MVA gas fired generators of which 2 are on standby. A diesel back-up generator is also available to supply critical needs